Pennhurst State Hospital: Spring City, PA
- On-Site coal fired power plant decommissioning
- 634 acre complex including 35 (2-5 story) buildings and concrete basements, underground tunnels
- Decommissioned former sanitary, wastewater treatment facility
- Planned decommissioning and removal of precipitators & associated piping systems
- Soil remediation, mold/asbestos removal, mitigation
- Planned crushing of over 42,000 tons of recycled concrete to be used as clean fill
- 20 month contract slated to be completed ahead of schedule
Embreeville State Hospital: Coatesville, PA
- On-Site coal fired power plant decommissioning
- 250 acre complex including 16 (4-6 story) buildings and concrete basements/underground tunnels
- Former sanitary, wastewater treatment facility closure/decommissioning
- Removal of antiquated brass boiler piping & systems
- Soil remediation, mold/asbestos removal, mitigation
- Crushed 60,000 tons of recycled concrete to be used as clean fill
- 18 month contract to restore entire property to “open space” community parks/fields
St. Luke’s Medical Center: Allentown, PA
Glaxo-SmithKline Discovery Labs Life Sciences: King of Prussia, PA
Jeanes Hospital: Philadelphia, PA
Promedica Pedestrian Bridge: Toledo, Ohio